Welcome everyone,
I need to have eleven V350's as stand alone plc's on our electric furnaces, except when we have an electric cutrailment. during the curtailment i need the master V350 to turn on two outputs to two of the slaves at a time, if we have more than two furnaces on during this time we will exceed our KW limit. i have the slave programmed to work just fine by them selves and have tried all of the help file examples to no avail. the problem is i need to implement this by June 1st. any help would be great. all i need is to get the Master/ Slave thing going. i have attached my slave file. the master file is so messed up even i'm confused. dont have time to fix it today the boss says i need to go we are off for easter weekend.
Thanks
Gary